Successful transverse launch of Ashton Arch bridge a South African first

7th October 2021

     

Font size: - +

The newly-completed Ashton Arch is South Africa’s first concrete tied-arch bridge constructed using a transverse launching method. Infrastructure consulting firm AECOM was responsible for all engineering aspects of the project, with the emphasis on road and bridge design, as well as project and construction management.

The aim of the project was to reconstruct parts of Trunk Road 31, from Ashton to Montagu (start of tourist Route 62), to a higher standard in order to improve traffic and pedestrian safety, as well as improve the flood capacity of bridges and the road at several problem locations.

Key considerations for the latest upgrading was to minimise flow restriction and improve the available free board within the restrictions of adjacent properties and road alignment levels. Through an economic analysis, the technical options for the river crossing and construction strategy were evaluated with due consideration of the impact of construction strategy on road user costs.

The design that was finally adopted consisted of a single span (110m) concrete tied-arch solution with a deck suspended by stay cables that accommodates four traffic lanes and two walkways. This largely eliminated the possibility of debris build-up and provided the shallowest deck depth option, both key considerations.

“The successful completion of the new Ashton Arch bridge resulted in a proud monument for the region and all involved. This was a first and unique application of this bridge engineering technique for a concrete tied-arch bridge in South Africa,” comments Abé Newmark, Executive, Team Lead - Bridges, Cape Town.

To minimise traffic disruption, the new bridge was constructed adjacent to the existing bridge while maintaining traffic over it. Upon completion, the new bridge was then used as a temporary bypass and river crossing, while the existing bridge was demolished and new abutments built. The new tied-arch bridge was launched transversely into its final position in less than 12 hours on 14 August 2021 under widespread publicity that included live-streaming of the event.

Structural form and bridge aesthetics received meticulous attention during the conceptual design, with due consideration of the following:

  • The historical significance of existing multiple-span arch bridges inspired the structural form, combined with the major benefit of the arch’s ability to span over the entire river.
  • A tied-arch bridge is particularly suitable for this topographic location.
  • V-hanger configuration for its aesthetic advantage.
  • Aesthetically, the slender tied-arch design is appropriate due to the visually-appealing light deck.
  • The tied-arch form expresses a visualisation of flowing of forces with light hangers.
  • Slender members displaying a transparency accentuated by the surrounding mountains.

State-of-the-art bridge analysis software packages were also used for the construction stage analysis, in-service analysis and design, a joint effort by AECOM’s SA and UK long-span complex bridge teams. An extensive structural behaviour monitoring plan was also prepared for construction.

Modern state-of-the-art structural components were designed, manufactured and installed using complex methodology. These included the post tensioned tie-beams, stay anchors and cables, as well as the transverse launching equipment, which had to be specially imported.

Many design, procurement and construction challenges were addressed over several years. Using a transverse launching method of a completed concrete tied-arch road bridge is a first in South Africa, when more than 8000t of concrete and steel was moved over a distance of 24m in less than 12 hours after several years of meticulous planning, design and construction.

Upon completion of the project, a total of 18% of the contract value would have been allocated to the creation of economic opportunities and entrepreneurial capacity in the surrounding areas. This included a local labour utilisation of 65 000 person days and 300 work opportunities created for exempted micro enterprises and qualifying small enterprises.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION