R487m N1 upgrade kicks off in Cape Town

12th February 2016

By: Irma Venter

Creamer Media Senior Deputy Editor

  

Font size: - +

The Western Cape Department of Transport and Public Works has started work on Phase 1 of a R487-million upgrade to the N1 freeway around Cape Town.

The main contractor is Martin & East.

Transport and Public Works Minister Donald Grant says the three-year project, which started on February 4, is expected to be completed in February 2019.

The project will include the addition of an extra lane to parts of the freeway that previously had two lanes, in an effort to decrease congestion.

Work will be carried out over the 9 km stretch of the N1, from Plattekloof road to just beyond the Old Oak interchange. This portion of the freeway belongs to the Western Cape government, and not the South African National Rail Agency, as is the case with most national roads.

This stretch of the N1 experiences severe congestion during morning and afternoon peak periods, with around 120 000 vehicles carried each day, says Grant.

Apart from the construction of additional lanes, the scope of the work, spanning four phases, includes the construction of new auxiliary lanes; the extension of the existing concrete median barrier to prevent head-on collisions; intersection improvements at various parts of the freeway; the demolition and reconstruction of the Old Oak West bridge and repairs to other bridges along the freeway.

The project will also include works to the existing water pipeline in the middle of the freeway.

All efforts will be made to ensure minimal disruption to traffic during the construction phase of the project, says Grant.

However, he warns that motorists should expect reduced general speed limits and lane widths in areas where construction work is taking place.

Project work hours have  been restricted to periods outside the morning and afternoon peak times.

Around R8-million of work in the project has been dedicated to the Emerging Contractor Development Programme, which forms part of the Expanded Public Works Programme.

Around R24-million has been committed to black business enterprises, and 29 000 person days set aside for labour sourced from the local area.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION