Proposed regulation lifting ‘embedded generation’ licence-exemption cap to 10 MW released for comment

23rd April 2021

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Mineral Resources and Energy Minister Gwede Mantashe has released, for public comment, an amendment to the Electricity Regulation Act, proposing an increase in the licensing-exemption threshold for embedded power generation plants from 1 MW to 10 MW.

The Gazette notice, which was published on April 23, follows President Cyril Ramaphosa’s February State of the Nation announcement that Schedule 2 of the Electricity Regulation Act would be amended to increase the licensing threshold for embedded generators.

The current cap is set at 1 MW, with projects above that size required to apply for a generation licence with the National Energy Regulator of South Africa.

Ramaphosa said that between 4 000 MW and 6 000 MW of additional generation capacity would be required over the next five years, over and above that which would arise from independent power producer procurement programmes and the completion of Eskom’s much-delayed coal projects.

“Recent analysis suggests that easing the licensing requirements for new embedded generation projects could unlock up to 5 000 MW of additional capacity and help to ease the impact of load-shedding,” Ramaphosa said, referring to a report produced by Meridian Economics in January.

The report, which gained the support of Eskom, proposed that the licence-exemption cap be increased to 50 MW, but Mantashe announced in March that it would be raised to 10 MW instead and called for Eskom to “stay in its lane”.

The proposed amendment also falls short of making some of the changes that the industry has been calling for with regards to wheeling of electricity to multiple customers.

Interested persons and organisations had 30 days, from April 23, to submit written comments to the Department of Mineral Resources and Energy on the proposed amendments.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION