Name of the Project
Prince Edward graving dock inner caisson rehabilitation.

Location
Durban, KwaZulu-Natal, South Africa.

Project Owner/s
Transnet National Ports Authority (TNPA).

Project Description
The project is among 11 large-scale projects earmarked for the Durban dry dock complex, of which the R48-million refurbishment of the dry dock’s 35-m-long, 900 t outer caisson, which closes off the dry dock from the rest of the harbour, was the first to be completed in 2016.

The project entails the repair of the inner caisson and upgrade of the drive system to ensure the safety of the dry dock and the sustainability of the ship repair business in Durban.

The rehabilitation includes major structural design improvements on rebuilt decks and compartments, which are being built in an off-site workshop.

Potential Job Creation
The project has created direct jobs for 29 skilled employees.

Capital Expenditure
The project is estimated at R61.5-million.

Planned Start /End Date
The project is expected to be completed in November 2020.

Latest Developments
The design and fabrication of the new steel sections have been completed.

The caisson has been taken apart at C and D deck levels while the A and B deck steel structures have been cut up for scrap.

The next big milestone will be to bring new sections of the C and D decks for installation on top of the rehabilitated DE section.

Key Contracts and Suppliers
Lodemann (managing contractor) and Channel Construction (design and build).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
TNPA corporate affairs manager Ayanda Somagaca, tel +27 31361 8527 or email ayanda.somagaca@transnet.net.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION