Precise Lifting Enables Smooth Refinery Expansion, Usa

16th July 2019

     

Font size: - +

Installation of three large pressure vessels was required at a refinery in the Texas panhandle in the USA. This work needed to take place with minimal disruption to the plant’s six-figure throughput and while utilising as little space as possible.

The three vessels were received on site by ALE and were each of a different size. The first was approximately 16m in length and 3.65m diameter (52ft 9in x 12ft); the second was 35m in length and 4m diameter (116ft x 13ft); the final vessel was 56m in length and 4.2m diameter (184ft x 14ft).

The smallest vessel was delivered under hook and tandem lifted by two hydraulic cranes with 100t (110 US tons) and 400t (440 US tons) capacities. This operation tailed up the vessel from its delivery trailer and set it on its foundations.

The mid-sized vessel was received by ALE in a laydown yard on site. From here, it was loaded onto SPTs fitted with bolsters and transported to its dress out location, adjacent to where it would be lifted and set in place.

Once dress out was complete the vessel was weighed, establishing its centre of gravity. It was then attached by its skirt ring to an SPMT with a 450t (496 US tons) capacity tailing frame, then tailed to a vertical position and again set on its foundations.

Due to its size and weight, the largest vessel was transloaded onto SPMTs using ALE’s 635t (700 US tons) capacity gantry lifting system. It was then transported to the dress out location, where it was rotated 60 degrees, having been shipped out of orientation. This rotation was performed using chain hoists in combination with the above gantry lifting system.

The final vessel was then tailed up in similar fashion, using a tailing frame mounted to an SPMT and a 1,350t (1,488 US tons) capacity crawler crane, with 84m (275ft) main boom configuration and a 560t (617 US tons) counterweight. The radius of all tailing lifts was 38m (125ft).

Equipment used during these lifts included 40 axle lines of SPMT, ALE’s Lift ‘N’ Lock gantry lifting system, 300t (330 US tons) capacity weightors, plus various pieces of staging equipment. The project also utilised LTM 1100 and 1400 mobile cranes and an LR11350 mobile crane.

The project allowed refinery activity to continue during installation. In particular, ALE’s custom transportation methodology for the largest of the three vessels ensured installation could take place without shutdown or rerouting of a large pipe rack on site.

The methodology used for all vessels also minimised working at height, as dressing out could take place at ground level prior to lifting. All three vessels will shortly be used to increase petroleum desulphurisation capability at the plant.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION