Lily solar + storage project, US

14th August 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Lily solar + storage project.

Location
The project is located south-east of Dallas in Kaufman County, Texas, in the US.

Project Owner/s
Enel Green Power.

Project Description
The Lily solar + storage project comprises a 146 MW ac photovoltaic (PV) facility, paired with a 50 MW ac battery.

Lily’s 421 400 PV bifacial panels are expected to generate more than 367 GWh/y, which will be delivered to the grid and will charge the co-located battery, equivalent to avoiding the emission of more than 242 000 t/y of carbon dioxide into the atmosphere.

The battery storage system can store up to 75 MWh at a time, to be dispatched when solar power generation is low while providing the grid with access to a clean supply of electricity during periods of high demand.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The project is expected to be operational by summer 2021.

Latest Developments
Construction in the project started in July 2020.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Enel Green Power, tel +39 06 8305 5699 or email ufficiostampa@enel.com.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION