Kangnas turbine installations completed ahead of schedule

19th March 2020

By: Tasneem Bulbulia

Senior Contributing Editor Online

     

Font size: - +

Kangnas Wind Farm on Tuesday completed the installation of all 61 wind turbines – two weeks ahead of schedule.

With all turbines now installed, the project is advancing to its commercial operations date, later this year.

The project developers point out that the 45-member crew that took on this large-scale lifting programme comprised mostly local South Africans from the Northern Cape province.

“Eighty-seven per cent of the lifting team are South African, with just six being expats. The team began the erection of the first of its 61 wind turbines in July last year and worked very hard to take advantage of the periods of low wind to install all the turbines, in just eight months and ahead of schedule,” explains Kangnas Wind Farm construction project manager Manie Kotze.

The next step in the development will be the handover of the two main power transformers.

“Once the two power transformers are installed and energised, commissioning and testing will commence on the wind turbines, followed by grid code compliance testing,” explains Kotze.

The 140 MW wind farm will have the capacity to generate 563.5 GWh/year of clean, renewable power into South Africa’s national power grid.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION