Johannesburg faces R17bn electricity infrastructure challenge
The undoings of the previous administration has resulted in the City of Johannesburg requiring an investment of around R17-billion over the next ten years to upgrade its ageing electricity infrastructure.
City of Johannesburg Mayor Herman Mashaba said his administration was facing serious infrastructure backlog challenges, compounded by an ageing network infrastructure, theft and vandalism, a backlog in asset renewal and bulk tariff trajectory.
“We have one electricity substation that supplies the entire inner city of Johannesburg. It is 75 years old, 30 years past its useful lifespan,” Mashaba said, referring to the almost 80-year-old Cleveland substation, which is now undergoing a R180-million refurbishment.
The city’s Van Beek substation is also using old switchgear that is difficult to operate and unsafe to use. It is also difficult to source spares for the substation.
“Some of our medium-voltage underground cables are 45 years old and the problematic areas include the inner city, Roosevelt, Parkhurst, Roodepoort and parts of Rueven. The replacement parts are difficult to source as some of the circuit breakers were installed in 1929,” said Mashaba.
He further highlighted that theft and corruption remained significantly challenging and was costing the city millions each year.
“Earlier this year, I shared how City Power had been robbed blind by a company that had been paid massive sums of money even though there was no real work on the ground to build substations in Hopefield and Eldorado Park.
“Just over a month ago, the inner city was plunged into darkness due to stolen underground cables,” said Mashaba.
About R76-million was spent on security measures in an attempt to curb cable theft and vandalism in the 2016/17 financial year.
The low-voltage overhead copper conductors are also being converted to aerial bundle conductors with the aim of solving the problem of power outages caused by cable theft.
Another challenge is the bulk tariff trajectory as “the Eskom tariff trajectory is going up and this causes an adverse impact on industry and residential areas. The city does not have sufficient budget for the renewal of bulk infrastructure. We are trying hard to attract investors. A total of R481-million is required to electrify formal and informal settlements over the medium term.”
Comments
The
content
you are trying to access is only available to subscribers.
If you are already a subscriber, you can Login Here.
If you are not a subscriber, you can subscribe now, by selecting one of the below options.
For more information or assistance, please contact us at subscriptions@creamermedia.co.za.
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation