Big loss for Gautrain predicted as ridership falls, owing to Covid-19

18th September 2020

By: Irma Venter

Creamer Media Senior Deputy Editor

     

Font size: - +

Weekday Gautrain rail ridership has fallen to 7 478 passenger trips a day, about 14% of pre-Covid-19 levels, says Gautrain Management Agency (GMA) COO Tshepo Kgobe.

Bus ridership is at 16% of pre-Covid-19 levels, at 2 974 passenger trips a day.

Midibus services are faring better, however, with ridership at 46% of pre-Covid-19 levels, at 864 passengers a day, notes Kgobe.

Does this fall in ridership mean that the Gauteng government will see a significant increase in the annual patronage guarantee (PG) payable by the GMA to the Bombela Concession Company as the Gautrain operator?

This guarantee increased from R1.34-billion in the 2016/17 financial year to about R1.5-billion for the 2017/18 financial year, for example, owing to a sudden decline in ridership. This happened for a number of reasons, such as a strike at Gautrain, noted former GMA CEO Jack van der Merwe at the time.

Kgobe says the PG has a cap set in the concession agreement with Bombela – in other words, there is a limit to the amount the Gauteng province has to pay in any month.

“This cap is the point at which Bombela takes the risk of revenue losses. During the lockdown, revenue decreased substantially, which meant that the PG increased to its cap and Bombela [was] exposed to the loss of revenue above the cap.”

Kgobe says the GMA is not yet able to quantify the current financial year’s PG.

“In the first quarter of the financial year, the province paid R92-million more than budgeted for the PG and Bombela lost approximately R171-million in revenue.”

Kgobe says Bombela and the GMA are working together to increase ridership on the system during the Covid-19 pandemic through a number of initiatives.

These include actively promoting the service to instil passenger confidence and reassure passengers that the Gautrain is safe; running the maximum number of eight-car trainsets, compared with four-car trainsets to ensure social distancing; and introducing midibus taxi services at various stations, while Gautrain bus routes are also being reviewed to augment the number of feeder and distribution routes around stations.

Plans are also in place for loyalty programmes and additional discounts for youth and the elderly in the form of a new student product and a travel card for the elderly.

Directional signages to all Gautrain stations are also being reviewed, as well as the concept of universal access.

“This includes improved safety and security in and around precincts,” says Kgobe.

“The Gautrain website and application are being upgraded for ease of customer experience.”

The payment of the PG is done in accordance with the project’s financial model, which was developed as part of the National Treasury’s approval of the Gautrain project as a public–private partnership.

This payment is included in the budget allocation of the GMA and forms part of the Gauteng provincial government’s medium-term expenditure framework.

The PG is a collective name for five components, namely the repayment of the equity and private-sector loans by Bombela, which were used during the development phase of the project; the cost of maintaining the system by the concessionaire; Bombela’s overhead costs, as well as the cost of replacing key components of the system in order to hand over the network in a prescribed contractual condition after the completion of the concession period – for example, the total bus fleet of 125 buses will be replaced during the concession period.

The PG also refers to an operation subsidy, which is used to top up the shortfall between the revenue received from the fare-box and value-add (such as advertising on the system), and the cost of operating the system.

For a number of years, the revenue received has been between 90% and 105% of operational costs – that is, until the onset of Covid-19.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION