Garden Route dam raising duckbill spillway increases capacity, enhances safety

12th June 2020

By: Schalk Burger

Creamer Media Senior Deputy Editor

     

Font size: - +

Engineering, design and advisory company Aurecon developed a duckbill spillway as part of the project to raise the Garden Route dam, which is the main supply for water-scarce George, in the Western Cape.

This not only increased the dam’s existing storage capacity by 25%, but also significantly increased the discharge capacity of the spillway to boost the dam’s safety by preventing overtopping.

This novel solution was developed owing to unique technical constraints. A duckbill spillway is a type of non-linear spillway, similar to the more generally-known labyrinth spillway, explains Aurecon Water Engineering Unit specialist and dam engineer Dr Frank Denys.

"The main aim is to increase the overflow length such that the spillway or weir can pass more flow for a given overflow depth. This allows for construction of very long spillways, typically four to five times longer than a linear spillway, in a limited area. The existing Garden Route dam spillway was only 25 m wide. However, the non-linear spillway extended this distance to 80 m by curving the spillway in the upstream direction."

Raising the dam’s water level was originally envisioned to be limited to increasing the overflow sill of the spillway, or installing some form of fusegate system on the spillway. These options were subjected to technical feasibility studies and an environmental-impact assessment. The various spillway gate options appeared attractive from a cost perspective, but undesirable when considering long-term maintenance.

Further, re-evaluation of the dam’s flood hydrology, following large flood events experienced in the recent past, resulted in flood peaks significantly higher than the original dam and the proposed gate options were designed for.

The updated hydrology required that the crest of the embankment also had to be raised to ensure its safety. A new spillway concept, with a significantly higher capacity than the previous alternatives, was devised to be able to pass the flood peaks with as low a head as possible to minimise by how much the embankment would need to be raised by, says Denys.

The 2.5 m raising of the full supply level (FSL) of the dam equates to an increase in the storage capacity by 2.5-million cubic metres for a total gross storage capacity of 12.5-million cubic metres.

“This will add much-needed drought resilience to the water-supply system. Expanding an existing water supply resource is also preferable to the development of new sites, as it limits the extent of the environmental impact to an already impacted site,” Denys notes.

Meanwhile, even though the FSL of the dam was raised by 2.5 m, as a result of the local terrain, the tallest portion of the new spillway wall is 4.9 m.

The main dam wall was raised 1.76 m by placing new earthfill on top of the existing embankment. This task had to be achieved in confined spaces, atop high slopes, mostly using available material of suitable quality from the dam basin, and some imported from commercial sources.

The spillway needed to have a high discharge capacity; however, extreme floods also have to pass underneath the road and main water supply pipeline bridge across the existing spillway to limit the high construction costs of raising this bridge, as well as consequent disruption.

"The sizeable and relatively flat approach channel allowed for construction of a fixed concrete weir that extends upstream from the existing spillway overflow and training walls. This resulted in the design of a trough or a labyrinth type of weir. Ultimately, the geometry of the site and hydraulic analysis led to the duckbill-shape spillway of the final design," says Denys.

The new sill is a reinforced concrete cantilever structure 4.9 m tall in places, which is unusual for hydraulic structures of this type as these are normally self-stable by their mass. To enhance the stability, the structure is provided with rockfill on the upstream side of the wall footing, in addition to rock anchors.

The rock of the channel in the centre of the duckbill had to be lined with concrete to prevent erosion. This slab also had to be held in place with rock anchors. Additionally, the foundation underneath the new spillway sill was grouted to reduce seepage underneath the wall.

The construction period was seven months, from May 13 to December 12, 2019. However, the various planning stages for the project date back over a decade, with the idea of raising the dam first being investigated as far back as 2004. The main client and dam owner is the George local municipality, with project funding from the Regional Bulk Infrastructure Grant.

Aurecon is currently in the process of rebranding as Zutari, after officially announcing the separation of the African business from the Aurecon Group, effective from January 1.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION