State-owned power utility Eskom has announced that its Unit 3 at Medupi power station is up and running following a 75-day outage to repair major design defects.

The unit has now reached its full generation capacity of 793 MW.

Eskom COO Jan Oberholzer explains that the major focus of the outage was to implement the technically agreed solutions for the boiler issues that hobbled the performance of the unit; these being the boiler plant modifications of the reheater spray flow, pulse jet fabric filter plant, gas air heater, milling plant, duct erosion and dust arrestors.

The unit is currently undergoing optimisation and performance testing, prior to conducting boiler performance verification tests, which require inspections and equipment tests to be conducted after 2 500 hours of operation, to verify the success of the modifications.

Eskom is implementing similar modifications on Unit 6 at the power station, which will be followed by repair works on Unit 1 starting later this month.

Further, Unit 4 at the power station will be taken off the grid in July for similar modifications, while Units 2 and 5 will be out for repairs in August and November, respectively.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION