Covid-19 forces changes to standard construction contracts, says MDA

28th July 2020

By: Irma Venter

Creamer Media Senior Deputy Editor

     

Font size: - +

Specialists in construction law MDA Attorneys say disruptions to business and operations owing to Covid-19 are no longer unanticipated, which means that all new contract negotiations have to take the possibility of this happening into account. 

“Initially, force majeure notices were being issued in line with the broad definition of force majeure as an unanticipated event,” says MDA Attorneys senior associate Barry Herholdt.

“However, we now know that even with regulated levels of lockdown a sudden announcement can impose stricter measures and regulations, which could limit or halt access to sites across the country. 

“We therefore need to reinvent our thinking when negotiating new contracts to create the right balance of risks in contracts with the understanding that Covid-19 and its effects will be with us for the foreseeable future.”

Using the most common occurrences, Herholdt identifies seven possible provisions that should be amended for better protection in the context of Covid-19.

Time extensions – with or without related costs
Identifying and stipulating likely delays entitles parties to claim extensions of time (with or without costs). Instructions for additional works (including variations) or to suspend or halt works completely, for instance, need to be anticipated and specified.

Access, mobilisation, demobilisation to and from site
Changes in lockdown levels may necessitate site alterations, including shutting down and reopening sites. Transport costs may rise on account of vehicle capacity restrictions for transporting workers to and from site and the location of the site is a key consideration as it could give rise to time implications. Cross-border and inter-provincial travel may be restricted, and regulated isolation or quarantine periods should be considered in addition to possible exemptions and permit requirements.

Health and safety considerations
Additional safety measures are required to protect workers and prevent the spread of the virus. A detailed stipulation of health and safety specifications needs to form part of every new contract, including guidelines and protocols, as well as agreement on related costs which become part of the contract value. Examples are hand-washing stations, sanitisers, screening equipment, personal protection equipment, restrictions on the sharing of tools, equipment and machinery and medical testing. The required period of isolation in quarantine should a worker test positive should also be anticipated. 

Price adjustment, escalation in supplier costs
Given the delays caused by supply chain interruptions, contracts should better define the circumstances which will establish a price escalation entitlement. The ability to utilise alternative and back-up suppliers to source required materials should be discussed. Shipping and delivery routes from the respective suppliers must be established to deal with possible border restrictions. 

Force majeure
Given that the presence and impacts of Covid-19 are no longer unforeseen, it is important to carefully review and expressly define what would constitute a force majeure event.  The detail in the wording is crucial, as some standard form contracts do not expressly stipulate “virus”, “epidemic” or “pandemic.” Also important to bear in mind is that claims under this clause generally allow for time extensions, but no additional related costs.

Insurance to be considered for proper cover relating to certain unforeseen events 
Parties need to consider insurance cover for loss of income or revenue, worker protection or worker salary protection and measures to accommodate alternative working environments, such as working from home. Other cover to be considered includes costs to provide access facilities to remote workers, security costs during periods with no access to site and cover for possible loss or delays incurred in the supply chain. 

Termination of the contract
The only certainty that has come with Covid-19 is that there will continue to be uncertainty, which makes it likely that parties may need to terminate the contract. The conditions for termination should be clearly set out, including notice requirements and the responsibilities and procedures each party should undertake.

 

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION