A contractor working at the Camden power station was arrested on November 16 after he was positively linked to an incident of sabotage following intensive investigative work by State-owned Eskom.

The perpetrator, who is employed by a maintenance company working at the power station, intentionally removed a bearing oil drain plug from a bearing, causing the oil burners to trip repeatedly, Eskom said.

The act caused all the oil to drain out from the bearing, thereby damaging the bearing which, in turn, prevented the mills from operating optimally.

Camden Unit 4 subsequently tripped after losing all the mills.

The incident occurred on November 10, and a case of alleged sabotage was immediately opened for investigation, at the Ermelo Police Station, Eskom confirmed.

It added that intensive internal investigations led to the culprit being identified and questioned about the incident.

“The evidence obtained, and the confession made by the perpetrator, revealed the plug was intentionally removed to cause the trip,” the entity said, adding that the act of sabotage would ensure that his employer is awarded additional maintenance and repair jobs at the power station.

“It is disheartening to find that some of our contractors are unscrupulous, have malicious intent and are willing to plunge the country into further loadshedding at a time when the electricity grid is highly constrained,” said Eskom security GM Advocate Karen Pillay.

“We have always suspected that some of our maintenance contractors and employees are behind these acts of sabotage. We shall continuously work with the law enforcement agencies to bring these insiders to book and ensure that justice is meted out, but most importantly that those with similar tendencies across Eskom are arrested and removed from the organisation,” she added.

The arrest, together with two last week where contractor truck drivers were arrested while in possession of stolen coal, are the result of persistent and excellent collaborative work by the Eskom Security Team and the South African Police Services, who are working tirelessly to identify and disrupt the criminal network.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION