Construction of Singida over 90% complete – Shanta

13th February 2023

By: Donna Slater

Features Deputy Editor and Chief Photographer

     

Font size: - +

East Africa-focused gold producer, developer and explorer Shanta Gold reports that the overall construction activity at its Singida gold project, in Tanzania, is 93% complete, with all essential equipment for operation of the gold mine now being delivered to site.

The stockpile of crushed ore has reached 32 300 t – equal to over one month of supply, significantly derisking the ramp-up period of operations.

The run-of-mine stockpile at the Singida process plant is currently 127 000 t at an average grade of 3.34 g/t, containing 13 581 oz of gold – equal to about four months of processing.

The installation of tailings storage facility high-density polyethylene liner for partial deposition is on track for completion in March.

Shanta also reports that the hot commissioning of the milling circuit is planned for later in February, while hot commissioning of the full process plant is planned for March.

CEO Eric Zurrin says the construction is on schedule for first production in March.

“The completion of this mine will transform Shanta Gold into a 100 000 oz/y producer, with a diversified resource base, derisking the balance sheet and providing the business with further financial flexibility,” he says.

Meanwhile, Shanta also notes that new GM and Singida mine leader George Kondela started working for the company in January.

He is a Tanzanian national with 24 years of mining experience, having worked with Barrick Gold, Randgold Resources, Mineral Deposits, Placer Dome and Pan Australian Resources.

Kondela is well known to the Shanta team over the last 20 years and previously worked with Shanta in 2019/20 before being recruited to Barrick.

He is a trained geologist and will also focus on reserve life expansion. At Singida, the existing resource base is significantly underexplored, possessing significant geological potential across various greenstone deposits.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION