Constitutional Court dismisses CoT appeal in contract dispute

21st May 2021

By: Creamer Media Reporter

     

Font size: - +

The Constitutional Court has dismissed the City Of Tshwane’s (CoT’s) application for leave to appeal in a dispute between Thobela Telecoms and CoT over the City’s allegations that the tender award process was unlawful owing to internal processes and procedures at the CoT not being correctly followed.

After the Supreme Court of Appeal (SCA) overturned, in September, a finding by the Gauteng High Court in Pretoria in July 2019 that set aside the awarding of a broadband contract to special purpose vehicle Thobela Telecoms, the CoT referred the matter to the Constitutional Court in December and sought leave to appeal the decision of the SCA.

“The judgement, handed down in the Gauteng High Court in Pretoria on July 16, 2019, related to the setting aside of the award of the Altron Nexus / CoT Municipal Broadband Network contract on the basis of primarily internal processes not having been followed by the CoT in the awarding of the tender,” Altron said in an update to shareholders.

The contract was awarded to Thobela Telecoms in June 2015, in which Altron Nexus is involved as the primary network designer and architect, supplier of broadband equipment and related services, as well as having a minority shareholding.

Altron appealed the matter in the SCA and the court ruled in favour of Altron.

“Given that the CoT had filed their leave to appeal outside of the rules of court, in an order dated May 19, 2021, the Constitutional Court refused the application for condonation brought by the CoT for the late filing of its leave to appeal application; additionally, the court dismissed the CoT’s application for leave to appeal with costs ordering that the application did not have any reasonable prospects of success,” Altron said in an update to shareholders.

“The board and management are pleased with the outcome of the Constitutional Court’s order and note that this risk and litigation has been mitigated and resolved accordingly,” the company concluded.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION