Name of the Project
S7 Expressway – Lot 3.
Location
The S7 will cross Poland from Gdansk, in the north, to Krakow, in the south. Lot 3 will extend between Widoma and Krakow.
Client
General Directorate of National Roads and Motorways (GDDKiA).
Project Description
The project involves the design and construction of 18.3-km-long stretch of the S7 Expressway.
Lot 3 will have four lanes, with two in either direction. Included in the project is the construction of 38 structures, including overpasses, bridges, animal crossings and a 2 km viaduct. The S7 will cross Poland from Gdansk in the north to Krakow in the south.
Potential Job Creation
Not stated.
Value
The contract is valued at about €250-million.
Duration
The project will take about 34 months to complete.
Latest Developments
Salini Impregilo has been awarded the contract to design and build Lot 3 of the S7 Expressway.
Key Contracts and Suppliers
Salini Impregilo (design and construction –Lot 3).
On Budget and on Time?
Not stated.
Contact Details for Project Information
GDDKiA, Jan Krynicki, tel +48 22 375 86 35, fax +48 22 375 87 63 or email jkrynicki@gddkia.gov.pl.