Rio completes Canadian hydropower project

2nd December 2022 By: Esmarie Iannucci - Creamer Media Senior Deputy Editor: Australasia

PERTH (miningweekly.com) – Diversified miner Rio Tinto has marked the end of the Kemano T2 hydropower project, in British Columbia (BC), with the commissioning of a second tunnel to carry water into the Kemano Powerhouse.

The new, 16-km tunnel was filled up with water and produced its first megawatt of electricity in July after its construction was completed in May. Both T1 and T2 are now operating together, ensuring the long-term reliability of the power supply for Rio’s BC Works aluminium smelter in Kitimat and neighbouring communities.

Rio this week estimated that the project contributed approximately $850-million to the BC economy and employed approximately 340 people at its peak.

“The completion of a second tunnel to supply water to the Kemano hydropower facility will ensure the long-term, sustainable production of low-carbon aluminium at our smelter in Kitimat,” Rio BC Works director energy and watershed partnerships Andrew Czornohalan said.

“This extraordinary construction feat is the result of the work of generations of workers over three decades. Partnerships with local communities and the Cheslatta Carrier Nation have been instrumental in the project's success. I want to thank all our employees and contractors who worked so hard since day one to make this achievement happen.”

The original tunnel was developed in the 1950s and operated on its own for over 70 years. At the time, a 50-m-long intake stub-tunnel was also built at Tahtsa Lake, but the construction of the second tunnel only started in the early 1990s. The project was then halted in 1995 after 8.4 km, then restarted in 2018 to refurbish the initial portion of the tunnel and complete the last 7.6 km.

This final section of the tunnel took 30 months to dig, using a 1 300-t tunnel boring machine.

As part of the demobilisation of the project, Rio donated surplus equipment to local First Nations and community organisations in Kitimat, Terrace and across the Nechako Watershed, including avalanche equipment as well as swiftwater and marine survival suits for search and rescue teams.