Kayseri Integrated Health Campus project, Turkey

15th August 2014 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Kayseri Integrated Health Campus project, Turkey

Name and Location
Kayseri Integrated Health Campus project, Turkey.

Client
ATM Saglik Kayseri Yatirim ve İsletme Anonim Sirketi, a joint venture between YDA İnşaat Sanayi ve Ticaret of Turkey (75%), and INSO Sistemi Per Le Infrastrutture Sociali of Italy (25%).

Project Description
The Kayseri Integrated Health Campus covers a construction area of 464 095 m2, including 342 509 m2 of hospital buildings. It comprises a multispecialty main hospital with 1 083 general treatment beds and 200 psychiatric beds, a 200-bed centre for physical therapy and rehabilitation, a 100-bed high-security psychiatric hospital, an administration building and a technical service centre.

Value
The total cost is estimated at €420-million.

Duration
Completion will take three years.

Latest Developments
The International Finance Corporation (IFC) plans to provide $30-million in loan finance.

Key Contracts and Suppliers
IFC (loan finance).

On Budget and on Time?
Not stated.

Contact Details for Project Information
ATM Saglik Kayseri Yatirim ve İsletme Anonim Sirketi, tel +90 312 459 4400, fax +90 312 436 8279 or
email samed.kartci@yda.com.tr.
IFC, tel +1 202 473 3800 or fax +1 202 974 4384.