Kangnas Wind Farm and Perdekraal East Wind Farm, South Africa

21st September 2018 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Kangnas Wind Farm and Perdekraal East Wind Farm, South Africa

Name of the Project
Kangnas Wind Farm and Perdekraal East Wind Farm.

Location
The Kangnas Wind Farm is located near Springbok, in South Africa’s Northern Cape province. The Perdekraal East Wind Farm is located 80 km northeast of Ceres, in South Africa’s Western Cape province.

Client
The equity members of the projects include African Rainbow Energy & Power; H1 Holdings; local community members through established community trusts, with shareholding funded by other project equity partners; Lekela; Mainstream Renewable Power, along with a consortium of investors, such as the International Finance Corporation and the Rockefeller Brothers Fund; and Old Mutual Life Assurance Company.

Project Description
The project entails the construction of two wind farms with a combined capacity of 250 MW.

Kangnas will have a 140 MW capacity and Perdekraal East a 110 MW capacity.

The projects were awarded under the South African Department of Energy’s fourth round of the Renewable Energy Independent Power Producer Procurement Programme.

Potential Job Creation
Not stated.

Value
The projects represent an investment of about R6.6-billion.

Duration
The projects were expected to start construction in June 2018.

Latest Developments
The Perdekraal East wind farm is preparing for the start of major construction activity.

Once complete, the wind farm, which spans 3 055 ha, will comprise 48, 115-m-high wind turbines.

When operating at full capacity, it will generate an estimated 183 000 MWh/y of clean renewable energy.

Since achieving financial close in June, the construction team has been working on establishing site infrastructure, as well as the clearing and grubbing of roads and turbine foundations while also preparing to build the 42 km road on site.

While still in the early days of the project, construction project manager Glenn Hobson has said the construction team is “gearing up” and expects to have excavated four foundations by the end of September.


The Perdekraal East wind farm will eliminate about 410 000 t/y of carbon emissions, compared with traditional fossil fuel power plants.


Key Contracts and Suppliers
Absa (debt); Simmons & Simmons and White & Case (lenders’ legal adviser); Fasken and Stoel Rives (sponsor legal counsel); Concor and Conco (construction contractor) and Siemens Gamesa Renewable Energy (supply and installation of wind turbines).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Mainstream Renewable Power, tel +27 21 657 4040.
H1 Holdings, tel +27 21 201 6432 or email info@h1holdings.co.za.
Lekela, tel +44 203 301 6280 or email info@lekela.com.