Name of the Project
High Rock power plant aerating turbine installation project.
Location
North Carolina, in the US.
Client
Cube Hydro Partners.
Project Description
The project entails the provision and installation of three aerating chambers of 13.4 MW each.
The turbines increase the amount of oxygen in rivers by drawing air into the turbine.
The oxygen in the air is transferred to the water and increases the dissolved oxygen levels downstream.
Potential Job Creation
None stated.
Value
Not stated.
Duration
The first turbine is scheduled to be delivered in the second half of 2018 and will become operational at the beginning of 2019.
Latest Developments
Cube Hydro Partners has selected GE Renewable Energy to provide its proprietary aerating turbines.
Key Contracts and Suppliers
GE Renewable Energy (aerating turbines).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Cube Hydro Partners, tel +1 240 482 2700 or email chp@cubehydro.com.