Name of the Project
Grant Lake hydroelectric project.

Location
The proposed project will be located on Grant Lake and Grant Creek, in the Kenai Peninsula Borough, in Alaska, in the US.

Client
Kenai Hydro.

Project Description
The project proposes to construct an intake structure in Grant Lake, a pumped bypass flow system, a tunnel, a surge chamber, a penstock, a powerhouse, a tailrace channel with a fish exclusion barrier, a tailrace detention pond, access roads, a step-up transformer, a breaker, a switchyard and an overhead transmission line.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
None stated.

Value
None stated.

Duration
None stated.

Latest Developments
The Federal Energy Regulatory Commission has prepared an environmental-impact statement (EIS) for the project.

The deadline to comment on the draft EIS is December 10, 2018.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Kenai Hydro, email info@kenaihydro.com.