Etango-8 uranium project, Namibia – update

12th January 2024 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Etango-8 uranium project, Namibia – update

Photo by: Bannerman Energy

Name of the Project
Etango-8 uranium project.

Location
Erongo region of Namibia, about 30 km east-south-east of Swakopmund.

Project Owner/s
Bannerman Energy, through its 95%-owned subsidiary Bannerman Mining Resources. The remaining 5% is owned by Namibian charitable body One Economy Foundation.

Project Description
The Etango deposit will be mined as a conventional truck-and-shovel openpit operation through contract mining over an initial mine life of 15 years.

Maximum mining rates are estimated at 27-million tonnes a year, with average ore mined of about 7.6-million tonnes a year at a life-of-mine average stripping ratio of 2.22.

Average production is estimated at 3.5-million pounds a year of uranium, enough to power up to eight large nuclear reactors.

Total production is estimated at 52.6-million pounds of uranium oxide.

Potential Job Creation
The project will create about 760 Namibian jobs and a multiplier effect of up to 5 000 indirect jobs.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $209-million and an internal rate of return of 17%, with a payback of 4.1 years.

Capital Expenditure
Preproduction capital expenditure is estimated at $317-millon.

Planned Start/End Date
Not stated.

Latest Developments
Namibia's Ministry of Mines and Energy granted Bannerman Energy a mining licence for its Etango uranium project in December 2023.

This has enabled Bannerman to award two key early works contracts: the construction of the temporary construction water supply and the site access road.

The temporary construction water pipeline will ensure sufficient water is available on site when the main earthworks and civil contracts start. The road will allow for controlled access to the mine site, with minimal impact on the surrounding area to be achieved from the start of full construction works.

The prompt award and start of these early works contracts also enables Bannerman to ensure that the current target construction schedule for Etango is maintained.

Key Contracts, Suppliers and Consultants
Wood plc (study lead – process plant design and related infrastructure, plant capital and operating cost estimates); Qubeka Mining Consultants (geology review, mining reserve estimate, mine planning and mining cost estimates); Snowden Optiro (mineral resource estimate); Creo Engineering Solutions (engineering support for Bannerman owner’s team); MineTechnics (openpit geotechnical parameters); Lund Consulting Engineers (water supply infrastructure); Addiza Energy Solutions (external electrical supply infrastructure); A.Speiser Environmental Consultants (environmental impact assessments); Namisun Environmental Projects & Developments (conceptual mine closure plan).

Contact Details for Project Information
Bannerman Energy, tel +61 8 9381 1436 or email info@bmnenergy.com.