Eskom’s Medupi Unit 4 synchronised to the grid

1st June 2017 By: Natasha Odendaal - Creamer Media Senior Deputy Editor

State-owned power utility Eskom on Thursday said Unit 4 at the Medupi coal-fired power station project, in Limpopo, had been synchronised to the national power grid this week.

This was the third of six units to come on stream and marked a key milestone towards the full commercial operation of the unit ahead of its scheduled commercial operation in 2018.

Unit 5 achieved successful synchronisation on September 8, 2016, and had reached commercial operation in April.

Medupi Unit 6 became commercially operational in 2015.