Name of the Project
El-Dabaa nuclear power plant (NPP).
Location
El-Dabaa, in Egypt, on the Mediterranean coast.
Project Owner/s
The Ministry of Electricity and Energy, represented by the Egyptian Nuclear Power Plant Authority (NPPA).
Project Description
The El-Dabaa NPP will be the first nuclear power plant in Egypt. The project will involve the construction of an NPP comprising four Russian-designed VVER-1200 pressurised water reactors.
With a nameplate capacity of 4.8 GWe, the plant is expected to account for up to 50% of Egypt’s power-generation capacity to meet the country’s increasing demand for electricity.
Potential Job Creation
Not stated.
Capital Expenditure
Not stated.
Planned Start /End Date
Unit 1 started construction in July 2022, and Unit 2 in November 2022. Applications to build units 3 and 4 were submitted in January 2022. Unit 3 was awarded a construction licence in March 2023.
Latest Developments
First concrete has been poured into the foundation slab at Unit 3 of the El Dabaa NPP, marking the start of the main construction phase.
Key Contracts, Suppliers and Consultants
Rosatom (pressurised water reactors); Atomenergomash and General Electric (turbine hall equipment); KHNP (construction of turbine islands); and Doosan Enerbility subcontractor – turbine islands).
Contact Details for Project Information
NNPA, tel +20 22633553 or email contact_us@nppa.gov.eg.