ContourGlobal Cap des Biches thermal power plant project, Senegal

26th September 2014 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Name and Location
ContourGlobal Cap des Biches thermal power plant project, Senegal.

Client
ContourGlobal.

Project Description
The project involves the rehabilitation of an existing brownfield site and construction of a new 53 MW thermal facility under a 20-year power purchase agreement (PPA). The new facility will be designed to burn heavy fuel oil and natural gas.

ContourGlobal will install Wärtsilä 18V46 high-efficiency engines, a technology that has been used by ContourGlobal in Togo and Rwanda. The engines will be coupled with a steam-turbine technology known as flexicycle to increase the generation capacity, thereby further reducing the cost of electricity.

On completion, it will be the lowest-cost liquid fuel and natural-gas-fired power plant in Senegal.

Value
€85-million.

Duration
Completion is expected in 2015.

Latest Developments
In August, ContourGlobal signed an agreement with the Senegalese national utility, Société Nationale d’Electricité du Sénégal, to rehabilitate an existing brownfield site and construct a new thermal facility under a 20-year PPA.

Key Contracts and Suppliers
Wärtsilä d (engines).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Contour Global, tel +221 33 889 1412 or Africa.inquiry@ContourGlobal.com.