Cilacap refinery upgrade project, Indonesia

8th July 2016 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Cilacap refinery upgrade project, Indonesia

Name and Location
Cilacap refinery upgrade project, Java, Indonesia.

Client
PT Pertamina (Persero) and Saudi Aramco.

Project Description
The project involves the capacity expansion of the Cilacap refinery to 370 000 bbl/d.

In addition, petrol and diesel production will be maximised, and the refinery will produce higher-quality base oils to be
sold domestically.

The upgrade will also enhance the petrochemicals capacity of the refinery to exceed more than 600 000 t/y of aromatics and 160 000 t/y of polypropylene.

The upgrade of the Cilacap refinery is part of Pertamina’s Refinery Development Master Plan to improve Indonesia’s energy security and involves the expansion and upgrade of its domestic refineries.

Value
The project is expected to cost between $4-billion and $5-billion to complete.

Duration
The front-end engineering design stage is expected to be completed in 2018, with the start of the engineering, procurement and construction phase expected to start in 2019.

The project upgrade is targeted for completion by the end of 2022.

Latest Developments
Amec Foster Wheeler Energy has been awarded an engineering and project management services contract to undertake the basic engineering design study for Cilacap refinery upgrade.

The group will develop the scope for the proposed upgrade project for the existing refinery and will finalise the process configuration and licensors’ packages over the next nine months.

Key Contracts and Suppliers
Amec Foster Wheeler Energy (basic engineering design study).

On Budget and on Time?
Not stated.

Contact Details for Project Information
PT Pertamina, email pcc@pertamina.com.
Saudi Aramco, tel +966 13 872 0115, fax +966 13 873 8190 or email international.media@aramco.com.
Amec Foster Wheeler Energy, tel +62 21 315 9040.