Central utility plant 4 – Phase 1, Thailand

23rd March 2018 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Central utility plant 4 – Phase 1, Thailand

Name of the Project

Central utility plant 4 – Phase 1 (CUP4.1).

Location

Rayong, Thailand.

Client

Global Power Synergy Public Company (GPSC).

Project Description

CUP4.1 is a 48 MW, 140 t/h gas-fired cogeneration power plant project.

This first phase of the project comprises one gas turbine; one heat recovery steam generator (HRSG) with a supplementary firing, steam and power distribution network to industrial consumers; and auxiliary systems to support future expansion.

Potential Job Creation

Not stated.

Value

Not stated.

Duration

Not stated.

Latest Developments

GPSC has awarded Pöyry an owner’s engineer services contract for CUP4.1.

The contract includes assistance in project management, design review, site supervision services and quality assurance, as well as and control and commissioning supervision.

The overall time schedule for Pöyry’s services is about 2 years.

Key Contracts and Suppliers

Pöyry (owner’s engineer services contract).

On Budget and on Time?

Not stated.