Name of the Project
Cement clinker production plant.

Location
The plant will be built in the Souss Massa region near Tidsi, situated about 65 km south-east from the regional capital Agadir, Morocco.

Client
LafargeHolcim.

Project Description
The project entails the construction of a new 3 500 t/d cement clinker production plant.

Potential Job Creation
Not stated.

Value
Not stated.

Duration
Start-up of the plant is scheduled for the first half of 2020.

Latest Developments
thyssenkrupp Industrial Solutions has won a contract from LafargeHolcim for the supply of the cement clinker production plant.

thyssenkrupp will provide engineering, procurement and construction (EPC) for the entire clinker production line, ranging from raw material preparation to clinker storage, and a grinding facility for solid fuels. The main components include a 1 000 t/h primary crusher, a longitudinal additives storage facility, a circular stockpile with a storage capacity of 12 000 t, a roller mill with an output of 290 t/h and a blending silo of 4 600 t.

Key Contracts and Suppliers
thyssenkrupp (EPC).

On Budget and on Time?
Not stated.

Contact Details for Project Information
LafargeHolcim, email media@lafargeholcim.com.