Cabinet approves development zones for future renewables projects

18th February 2016 By: Terence Creamer - Creamer Media Editor

Cabinet approves development zones for future renewables projects

Photo by: Duane Daws

Cabinet this week approved the Gazetting of the Renewable Energy Development Zones (REDZs), which it claimed would help streamline regulatory processes surrounding the development of renewables projects, while also directing transmission infrastructure investment.

The REDZs were identified following a Strategic Environmental Assessment conducted by the Council for Scientific and Industrial Research. Cabinet described them as specific geographic areas where wind and solar photovoltaic (PV) projects would be incentivised and where “deep grid expansion” would be directed.

The announcement came following four competitive bid windows under government’s Renewable Energy Independent Power Producer Procurement Programme, which had resulted in the procurement of nearly 7 000 MW of renewables capacity across 92 projects.

The programme had resulted in investments or investment commitments of R193-billion since the conclusion of the first bid window in November 2011.

In addition, tariffs associated with wind and solar PV projects had fallen materially. Wind tariffs fell from R1.42/kWh in the first bid window to 65 c/kWh in the fourth, while solar PV tariffs fell from R3.44/kWh to 82c/kWh over the same period.

However, with every successive bidding round, it had become increasingly difficult to secure grid-connection capacity and grid quotations from Eskom, which operates South Africa transmission infrastructure.

The limitation had already led to delays in the finalisation of the most recent bid windows, with Eskom initially holding back from the issuance of grid-connection budget quotes. In November, it began issuing quotes again, but the utility had stressed that it was not in a position to issue quotes for bid windows beyond 4 and 4.5, also known as the expedited round.

Eskom confirmed, however, that a Strategic Grid Plan was being developed in parallel to the identification of REDZs in a bid to align grid development more closely with solar and wind energy resource locations.

The five corridors, each 100 km in width and traversing the entire country, had been identified. The corridors also reportedly take account of expected changes to South Africa’s electricity generation mix, which is currently dominated by coal-fired power stations located in the north-eastern regions of the country.

“These REDZs will ensure a transition to a low-carbon economy, accelerate infrastructure development, and contribute to a more coherent and predictable regulatory framework that reduces bureaucracy related to the cost of compliance,” Cabinet said in a statement.