Name of the Project
Bussy-Saint-Georges hydrogen and multi-energy filling station.

Location
Bussy-Saint-Georges, greater Paris, France.

Project Owner/s
Bussy-Saint-Georges and partners, Lhyfe, and Thevenin & Ducrot.

Project Description
The project entails the construction of a green and renewable hydrogen production site and an 8 500 m2 multi-energy filling station.

The site will be the biggest green and renewable hydrogen production site in France, with a production capacity of 2 t/d and installed capacity of 5 MW, and the first in the region to offer hydrogen delivery in containers.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The production site and filling station are expected to be commissioned in 2026.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Lhyfe industry press relations, Clémence Rebours, tel +33 6 60 57 76 43 or email c.rebours@nouvelles-graines.com.
Thevenin & Ducrot head of alternative energies Benoit Guard, tel +33 7 88 80 93 24 or email b.guard@thevenin-ducrot.fr.
Mayor’s Office of Bussy Saint-Georges communications, email Maeva Hiron, tel +33 6 29 83 87 21 or email maeva.hiron@bussy-saint-georges.fr.