Name of the Project
Breogan project.

Location
Curtis-Teixeiro industrial area, in Galicia, Spain, where Greenalia has its 50 MW biomass plant.

Project Owner/s
P2X-Europe and Greenalia.

Project Description
The proposed facility will produce synthetic crude oil for aviation, and is expected to produce 11 000 t/y of green hydrogen from renewable sources that, together with the capture of 70 000 t/y of biogenic carbon dioxide ( CO2) from Greenalia’s biomass plant, will produce an estimated 20 000 t/y of synthetic crude.

These crudes will be refined into e-fuels (eSAF and eDiesel) and synthetic waxes to serve the decarbonisation of the aviation and transport industry, and the chemicals and pharmaceuticals industry. The  CO2 capture for this project is equivalent to planting one-million trees.

Potential Job Creation
Not stated.

Capital Expenditure
€200-million.

Planned Start/End Date
The project is expected to start operating in 2027.

Latest Developments
Not stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
P2X-Europe, tel +49 40 370047631 or email info@p2x-europe.com Greenalia (Europe), tel +34 900 81 50 81.