Bad Lauchstädt Energy Park, Germany

1st September 2023 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Bad Lauchstädt Energy Park, Germany

Name of the Project
Bad Lauchstädt Energy Park.

Location
Bad Lauchstädt (Saxony-Anhalt), Germany.

Project Owner/s
A consortium comprising Terrawatt, Uniper, VNG Gasspeicher, ONTRAS, DBI and VNG.

Project Description
The Bad Lauchstädt Energy Park will produce, transport, store and use green hydrogen with 30 MW of electrolysis powered by a nearby wind farm.

The project includes the conversion of a gas transport pipeline and the construction of a new airlock for introducing pigs to the network.

The pipeline connection to the energy park will give Total’s Leuna refinery access to the future European hydrogen infrastructure and the international markets for green hydrogen.

Potential Job Creation
Not stated.

Capital Expenditure
€240-million.

Planned Start/End Date
Construction started in June 2023.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Bad Lauchstädt Energy Park project manager Cornelia Müller-Pagel, tel +49 341 443 2961 or email info@energiepark-bad-lauchstaedt.de.