Akademik Lomonosov floating nuclear power plant project, Russia

19th August 2016 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Akademik Lomonosov floating nuclear power plant project, Russia

Name and Location
Akademik Lomonosov floating nuclear power plant (FNPP) project, Russia.

Client
Rosenergoatom.

Project Description
The project entails the construction of the first FNPP – Akademik Lomonosov – with a capacity of more than 70 MW.

The plant will begin its operation in the most northern part of Russia, but can be operated anywhere in the world.

The FNPP is a mobile power unit, providing energy generation where and when it is needed.

Its construction is based on Rosatom’s icebreaker power units that operate in the Arctic, but unlike them, the unit is not self-propelled and has to be hauled on water to its destination point.

The FNPP is then connected to on-shore infrastructure to provide settlements with electricity and heat.

The FNPP is designed to supply power to port cities, major industrial enterprises and offshore complexes producing oil and gas.

The nuclear thermal power plant comprises two reactor units.

The floating power unit (FPU) is a nonself-propelled rack-type vessel with a double bottom and sides, as well as superstructure.

The unit is designed to work long distances from populated settlements if necessary.

A central energy compartment, with two KLT-40 reactor units, and a compartment for reloading and storing spent fuel, is located in the FPU.

In the bow there are engine rooms and several switchgear power conversion rooms. There are stern rooms for emergency diesel generators, backup diesel generators and living quarters.

The FPU hull is built as a pontoon, with pointed nose and tip, and a transom stern.

The FNPP includes the FPU, hydraulic utilities and on-shore area.

Hydraulic utilities include a pier berth, protecting the FPU from external influences; mooring posts, providing reliable fastening of the FPU; and a connecting pier, facilitating the transfer of thermal and electrical power, as well as communications, to the shore.

The on-shore area will include a transformer station and switchgear; process buildings and facilities, with a central heat distribution station, as well as equipment to prepare and transfer the thermal energy to consumers; an office building; buildings and facilities to ensure complex physical protection; and utilities going from the FNPP to the shore.

The FPU also includes accommodation for 70 people, a dining room, a lounge, a conference room, an information centre, a library, a smoking room, a sports complex, a lounge with a bar, a hairdresser and a shop, as well as a laundry and everyday services room.

Value
Not stated.

Duration
The FNPP will enter operation in 2019, in the City of Pevek, in Chukotka.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Rosenergoatom, tel +7 495 647 4189.