A 353 kW solar photovoltaic (PV) plant at turnout systems company voestalpine VAE South Africa’s Isando premises would supply between 40% and 45% of the company’s daily electricity requirements, CEO David Marite said.

He said that the company had invested about R8-million in the plant, which was officially launched and connected on Wednesday.

PV solutions provider SUNCYbernetics, in partnership with Germany-based SUNfarming, was responsible for its installation.

SUNCYbernetics junior technical design engineer and project manager for the voestalpine installation Faure van Schalkwyk explained that SUNfarming provided the technology and was the engineering, procurement and construction contractor for the project, while SUNCYbernetics handled the project development and project management aspects.

The installation of the plant’s about 1 400 solar panels, 700 of which faced west, started in May this year and was completed within a week, after which the alternating current installations were done, inverters and cabling installed and other finalising work completed Van Schalkwyk explained.

He said that, when installing solar PV plants of this nature, SUNCYbernetics sized the system in such a way that the customer uses most of the energy produced.

“We sized [the plant] as far as possible according to their normal use. All the electricity that is produced is used by voestalpine, and any extra electricity is reduced,” he said, explaining that this meant that no electricity would be supplied back into the Eskom grid.

Meanwhile, SUNCYbernetics had also signed a one-year maintenance contract with voestalpine.

Van Schalkwyk pointed out that this contract also included the cleaning of the system, which was necessary after testing found that dirt on the modules could result in a 10% to 15% loss of generation capacity.

“In terms of the cleaning, we will have a monitoring system in place. Once the performance is less than a certain percentage, we will send out a team to clean the panels,” he said, adding that SUNCYbernetics was also doing research in conjunction with North West University on how to best clean the panels.

Meanwhile, Marite explained that voestalpine’s installation of the PV plant was in line with the greater voestalpine group’s drive to be more conscious about the use of green energy.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION