Brigg renewable-energy plant project, England

21st March 2014

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Brigg renewable-energy plant project, Lincolnshire, England.

Client
The power plant is being built by BWSC – a collaboration between Burmeister & Wain Scandinavian Contractor (BWSC) and PensionDanmark. BWSC will also be responsible for the operation and maintenance of the plant for 15 years.

Project Description
The project involves the construction of a 40-MW-capacity power plant, which will be primarily fuelled using locally sourced straw. The plant is expected to produce enough energy for 70 000 households and will result in yearly carbon dioxide emission reductions of about 300 000 t.

The plant will be based on energy technology developed in Denmark. A boiler, supplied by high-tech company BWE, will primarily be used for firing straw and will form the core of the plant.

The steam created through the firing of straw will be conducted to a turbine generator, which will produce electricity for households and businesses in the vicinity.

Value
£90-million.

Duration
The plant is expected to be operational from early 2016.

Latest Developments
Alstom has signed a contract with BWSC to design and supply a 45 MW geared reaction steam turbine (GRT) for the Brigg renewable-energy plant, in the UK.

Alstom has optimised the GRT for efficient and flexible power production, covering renewable and traditional fuel types, in addition to industrial applications for process steam. It features a flexible modular concept and a plug-and-play package to reduce installation time.
Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
BWSC, tel +45 48 14 00 22, fax +45 48 14 01 50 or email bwsc@bwsc.dk.
Alstom, Stéphanie Grange,  +33 1 41 49 78 62.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION