A Re Yeng – Tshwane Rapid Transit system, South Africa

29th August 2014

  

Font size: - +

Name and Location
A Re Yeng – Tshwane Rapid Transit (TRT) system, Gauteng, South Africa.

Client
City of Tshwane.

Project Description
The Tshwane bus rapid transit (BRT) system, known as A Re Yeng, or Let’s Go, forms part of the City of Tshwane’s 2055 Growth and Development Strategy.  The City of Tshwane has established a set of objectives to transform the public transport system by providing high-quality, yet affordable, public transport.

The 56 km of trunk route, featuring BRT buses in dedicated lanes stopping at dedicated stations, will run from Wonderboom to Denneboom, with passengers transported to trunk route stations using complementary or feeder routes.

The entire BRT system will link Kopanong, in the north-west of Tshwane, to Denneboom, in the north-east, following a u-shaped route and traversing the inner city.

TRT Phase 1 will be completed in five infrastructure construction phases.

The 7 km, Phase 1A leg of the BRT system will run from Nana Sita, in the central business district (CBD), to Hatfield.

It is expected that Phase 1A of the system will ramp up to transporting 7 800 passengers a day, with the final system running at 136 000 passenger trips a day in 2017. During this phase, about 30 buses will operate and provide direct services between the CBD and Hatfield, with buses running every seven minutes along this trunk corridor. Feeders will also serve the corridor, running at 15-minute headways and docking with the trunk stations at Nana Sita 1, Sunnyside 1 and Sunnyside 2 stations.

Phase 1B will run from Hatfield to Menlyn and Phase 1C from the CBD to Rainbow Junction.

The Tshwane BRT comprises 18 m articulated buses, each carrying 90 people, and 12 m buses, each carrying 60 people.

An estimated 174 buses will be procured for the system and will comply with the latest European emission standards. The city has further approved a decision to roll out compressed natural gas fuel for at least 30% of the TRT bus fleet, after Phase 1A. This is part of the city’s commitment to reduce carbon emissions while driving sustainability.

The low-floor buses are easily accessible to children, the elderly and people with disabilities.

The City of Tshwane has chosen two designs for the stations.

Memory Box concept stations will be located in the CBD. They will include imagery and information on the historic buildings surrounding them.

The Retro-Tram design will be used for the stations located outside the CBD. The concept is intended to evoke the imagery of the city’s historical tram lines, realised in a modern style.

Payment on the BRT system will be by smartcard and should be compatible with other public-transport smartcard systems.

Value
The City of Tshwane has secured R3.2-billion in funding from national government over the next three years.

Duration
Construction for Phase 1A of the city’s TRT system, which will be rolled out in 2014, has started. The system is officially on track according to the milestones and timelines outlined for the Hatfield station project, for which the sod-turning ceremony took place in July 2012.

Phase 1B – Hatfield (University road) to Menlyn, or the BRT line 2B – is expected to be completed in March 2016.

Phase 1C – the CBD (Scheiding street) to Menlyn, or the BRT line 1A – is scheduled for completion in August 2015, and the Rainbow Junction to the Akasia-Kopanong section, or BRT line 1B, in October 2016.

Phase 1D – Menlyn to Denneboom station, or BRT line 2C – is scheduled for completion in June 2017.

Latest Developments
The City of Tshwane aims to roll out 171 buses by November as part of the inception phase of its BRT system to establish additional stages and introduce further buses if there is demand.

This is according to bus operating company Tshwane Rapid Transit (TRT) CEO Bukeka Mahlutshana.

TRT, a private company, was contracted in 2012 by the City of Tshwane to operate the BRT planning and run the inception phase of the system, which included the roll-out of an initial 30 buses.

The three-year inception phase, which is expected to begin in November, will enable the city to identify the taxi and bus operators affected by the BRT system and integrate them into the system by offering them jobs as BRT drivers.

At least 48 drivers from the taxi industry have been employed as part of the inception phase and have undergone extensive training to operate the buses.

TRT has spent three months with the selected taxi drivers to explain the long-term relationship with the company and the benefits of becoming bus drivers for the BRT system. The driver contract is valid for15 years, which ensures job security and opportunities for growth in the company.
TRT deputy chairperson Piet Mahlangu hopes the image of the taxi industry will improve following the inception of the BRT system. He further states that a backlash is not expected from the taxi industry regarding the implementation of the BRT system in Tshwane.

Mahlangu adds that TRT is exploring all opportunities that arise from the implementation phase and hopes that people in the taxi industry will be the primary beneficiaries of such opportunities.

The inception phase of the BRT system will be followed by a 12-year contract between the city and TRT, the latter of which will be contracted to run the buses as Tshwane’s management company.

The contract is being negotiated on a rate-by-kilometre model.

Key Contracts and Suppliers
Lonerock Construction (BRT Line 1A: Roadway – Pretoria street to Venter street); Mivami Construction (BRT Line 1A: Roadway – Venter street to Louis Trichardt street); Vharanani Properties and Boitshoko Road Surfacing joint venture (BRT Line 1A: Roadway – Louis Trichardt street to Rainbow Junction); seven contractors from the Contractor Development Programme (BRT Line 1C: NMT Facilities  – Kopanong station); Superway Construction (BRT Line 2A: Roadway  – Nana Sita street); Bophelong Construction (BRT Line 2A: Roadway – Kotze street to Lynnwood/ University road) and Bona Consulting (urban traffic control).

On Budget and on Time?
Yes.

Contact Details for Project Information
TRT project leader Lungile Madlala, tel +27 12 358 4091, fax 086 241 8303 or email  lungilem@tshwane.gov.za.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION