R30m caisson repair project for Durban dry dock

31st July 2015

By: Shirley le Guern

Creamer Media Correspondent

  

Font size: - +

Durban’s ageing dry dock will be closed for two months while Transnet National Ports Authority (TNPA) completes a R30-million repair to its badly corroded outer caisson.

Deputy port engineer Dumisani Mkhize told a press briefing in Durban last week that routine maintenance had revealed that it was in “a severe” state of “structural disrepair”.

He said it had been decommissioned and moved to the back of the dry dock. The tank section is removed and completely rebuilt to its “original design condition”.

The Prince Edward graving dock, which was conceptualised in 1911, was originally built for the Royal Navy. It was commercialised in June 1925. It has two caissons. The inner one is used to seal off the entire dry dock during the repair.

Mkhize and Durban port manager Moshe Motlohi said that the poor state of the dry dock was due to its age, as well as to maintenance and upgrades having not been high on the TNPA priority list until now.

The entire repair, which would take four months, had been structured so that the dry dock itself was only out of commission during August and September. It would reopen on October 6.

“The contractor’s preferred method required a four-month nonoperational period of the dry dock. However, TNPA has implemented a contingency plan to reduce this to two months in order to minimise the impact on industry. We have thoroughly investigated various methods, including the option to keep the dry dock operational during the entire project.

“We are confident that the method we have adopted will afford protection against risks such as endangering the structural integrity of the caisson and dock, escalating costs and, the prolonged duration of the project,” Motlohi explained.

After the hospital ship Africa Mercy , which is currently in the dry dock for repairs, leaves, no vessels have been booked in until the October 6 reopening.

TNPA expects the Durban dry dock outer caisson repair to be completed in November. This will then replace the relocated inner caisson. It will be commissioned when the next vessel departs from the dry dock in November.
Durban-based Channel Construction, which won the tender for the project, will work 24-hour shifts, with the bulk of the work being carried out off-site at its Bayhead workshop.

The refurbishment will include demolition and waste disposal, structural repair, welding, modification and the replacement of structural members and plates, design and fabrication certification, commissioning and final handover.

MD Hafzal Razak said the tender would create 43 new jobs on site and 26 additional positions in the company’s workshop.

Motlohi said the caisson repair marked the beginning of further investment in the Durban dry dock, which had been earmarked as a job creator and business generator through the revitalisation of the ship repair industry in Durban.

The dry dock’s current market included cargo vessels and TNPA’s own fleet of marine vessels.

Last year, the dry dock accommodated just 37 vessels but this was expected to increase with upcoming investments.

These will include a concrete refurbishment programme, the replacement of crane rails, the replacement of two aged electrical overheard cranes and the refurbishment of the inner caisson.

New Jib cranes, an upgrade of the mechanical pumphouse, the replacement of workshop equipment, the installation of a new firefighting system, the installation of new capstans, the replacement of the nonoperational floating dock and the procurement of six compressors were also planned.

He pointed out that TNPA had identified projects valued at R16.8-billion to facilitate the growth of the local ship repair, ship building and the oil and gas sectors. All should be operational by 2019.

To refurbish existing ship repair facilities, TNPA will invest about R2.2-billion in mechanical, electrical and civil infrastructure upgrades at the ports of Durban, East London, Port Elizabeth, Cape Town and Mossel Bay.

Greenfield projects worth R14.6-billion will include new capacity creation at the ports of Saldanha Bay, Richards Bay and East London. These will be cofunded through public–private partnerships.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION