Italian metallurgical process plant and mechanical construction company SMS Meer was contracted in February by Spanish steel producer ArcelorMittal Asturias to revamp the 150 t/h walking beam furnace, which feeds the steel company’s wire-rod mill.

The aim of the project is to reduce the plant’s operative costs to increase competitiveness. The revamp will achieve 80% natural gas savings and lower emissions, as well as improve productivity and flexibility.

The project mainly involves redesigning the combustion equipment, which currently runs on 100% natural gas, by introducing the possibility of also combusting blast furnace gas.

The new combustion equipment will provide the user with the flexibility to use a mixed bag of variable percentages of natural gas and blast furnace gas, with the latter being preheated by a new recuperator. Thus, the new system will enable the steelmaker to save about 80% of its current natural gas consumption.

The technical approach has been jointly developed by SMS Group and ArcelorMittal engineers over several months of close collaboration, balancing the needs to save fuel, decreasing the company’s pollutants emissions and accomplishing the complete revamping job in a short time.

According to the challenging schedule of this turnkey job, the furnace will be fully operational again in September, after just one month of mill stoppage.

The project will also provide ArcelorMittal with the opportunity to completely update the furnace combustion system to the latest European safety regulations.

With the new equipment, any grade of iron will be able to be reheated without any limitations. The billet dimensions are 150 mm × 150 mm and 180 mm × 180 mm, from 12 000 mm to 15 200 mm.

Further, the system will be constantly managed by Prometheus, the advanced combustion optimisation system recently developed by SMS Group.

This system allows for targeted improvements of the metallurgical properties. For example, it increases temperature uniformity and minimises steel decarburisation and high-scale formation.

Prometheus will also help SMS Siemag reduce fuel consumption by adopting heating strategies that minimise the temperature set points, yet guarantee that the required temperature of the final stock target is attained.

Edited by Samantha Herbst
Creamer Media Deputy Editor

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION