Gibela rail plant on track for March completion

15th December 2017

By: Irma Venter

Creamer Media Senior Deputy Editor

     

Font size: - +

Construction of the Gibela plant, in Dunnottar, on the far East Rand, is on track for completion in March next year, says Gibela Rail Transport Consortium CEO Thierry Darthout.

Darthout, former Gibela operations VP, took over the reins from Marc Granger on August 1. The 53-year-old is a mechanical engineer by training and has worked for Alstom for 19 years in various fields.

Alstom Southern Africa is the majority shareholder in Gibela (61%), while black economic-empowerment partners New Africa Rail and Ubumbano Rail hold 9% and 30% respectively.

“We are in the process of commissioning the industrial equipment at the plant,” says Darthout. “The first prototype train is already under construction. The first locally built train should be delivered to the client in December 2018.”

The Gibela consortium has to deliver 600 new X’Ttrapolis Mega commuter trains (3 600 cars) to the Passenger Rail Agency of South Africa (PRASA) in a R59-billion deal signed and sealed in 2014. Local content on the trains is promised to be between 65% and 70% by volume.

Darthout says a particular challenge in providing the 600 new trains is that Gibela will have to build one train car a day in 2019, at the peak of production.

“And we’ll have to do this in a brand-new factory with new staff and a new supplier base.”

The technology used to produce the trains, however, is well proved and tested within the Alstom group.

Gibela has already identified and developed 100 local components suppliers for the project.

Some of these 100 companies will supply Gibela directly, while others will supply Alstom Ubunye, which will, in turn, supply a number of components to Gibela. These components include bogies, traction systems, converters, control systems and looming.

Alstom Ubunye is the former Nigel-based Commuter Transport & Locomotive Engineering. Alstom acquired 51% of the rolling stock refurbishment business in 2016.


“We now have to make sure all our suppliers reach sufficient maturity to supply Gibela at peak production,” says Darthout.

Gibela remains on the lookout for more suppliers, he adds. This is due to the consortium’s double-sourcing strategy.

“For each component, we need two suppliers. This is simply a risk-management strategy,” explains Darthout.

“We have the full range of parts available to Gibela already, and now we are busy developing a double sourcing strategy.”

A number of the 100 suppliers have already produced components for the first 20 trains that Gibela delivered to PRASA.

These trains were built by Gibela’s majority shareholder, Alstom, at its Lapa manufacturing plant, in Brazil. The last of the trains arrived in South Africa in July.

Eigtheen of these trains (two were test trains) are currently being operated by PRASA on the Pretoria–Koedoespoort–Pienaarspoort corridor.

“The feedback we have received from customers is that they are very happy with the product,” says Darthout.

The trains have already clocked more than 500 000 combined operating kilometres.


Another challenge that Darthout remains acutely aware of is one emanating from the communities surrounding the Dunnottar plant.

“These communities have high expectations of business and job opportunities and we are doing our best to manage these expectations,” says Darthout.

The plant project has already seen community protests demanding increased local involvement in the project. A dedicated Gibela team manages community affairs at the plant.

Employment at the plant will reach 630 people by March next year, peaking at 1 000 people, excluding employment at components manufacturers.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION