Medupi’s second unit powered for first time, generates 796 MW

20th December 2016

By: Ilan Solomons

Creamer Media Staff Writer

  

Font size: - +

State-owned power utility Eskom revealed on Tuesday that the second unit of its Medupi coal-fired power station, in Limpopo was loaded to full capacity over the weekend and generated 796 MW of electricity.

Eskom interim CE Matshela Koko said that this was Medupi’s most “significant achievement” since its successful synchronisation on September 8 and indicated that Unit 5 was getting closer to reaching commercial operation.
 
He said that the full load demonstrated the plant’s ability to meet design output after commissioning of all major plant [equipment] and the integration of this plant through the unit control system.
  
“We are pleased with this significant milestone and believe that power from this unit will go a long way in strengthening the power supply to the country. We commend the project team for their hard work and level of commitment in delivering the project and this achievement confirms our quest to ease the pressure on the national power grid,” Koko enthused.
 
Medupi Unit 5 is being progressively commissioned and optimised to ensure that the power it delivers is stable, consistent and reliable. Koko elaborated that during this final optimisation and testing phase, the unit was not expected to stay on load for long periods of time and would deliver power intermittently.

Medupi is a green field, coal-fired, dry-cooled, base load power station comprising of six units rated at 4 800 MW od installed capacity. Once completed, the power station will be the fourth largest coal-fired plant and the largest dry-cooled power station worldwide.
 
“Unit 5 will progressively be tested and fine-tuned further until the project team is satisfied that the systems are fully operable and reliable for final handover. This is also to ensure that the unit is safe to operate and will perform exactly as designed for the next 50 years,” Koko concluded.

To watch Creamer Media's latest video reports, click here
 

Edited by Megan van Wyngaardt
Creamer Media Contributing Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION