Mbeya coal-to-power project, Tanzania

8th April 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Mbeya (formerly Rukwa) coal-to-power project (MCPP), Tanzania.

Client
Kibo Mining.

Project Description
The project comprises two prospecting licences and two prospecting licence applications in south-western Tanzania, just south of Lake Rukwa.

Kibo is undertaking a twin-track development at Mbeya.

Rukwa has total in situ resources of 109.39-million tons of coal, with the coal to be fed into a 250 MW to 300 MW mine-mouth thermal power station.

Seven different coal seams exist for the Rukwa coal mine.

It has been proven that constant coal production over the total life-of-mine can be achieved.

Phase 2, Stage 1, of a prefeasibility study (PFS) on the intended Rukwa coal mine completed in August 2015 has identified four possible mining methods for the development of the mine.
– Option 1 – surface miner, contractor, no crushing.
– Option 2 – surface miner, owner mining, no crushing.
– Option 3 – free dig, contractor mining, crushing.
– Option 4 – free dig, owner mining, crushing.

The differences in the options are mainly attributable to alterations in mining operating costs and mining capital costs, with the project financially feasible for all the options.

The mining project has been assessed for a 28-year mine life, with average coal production estimated at 1.48-million tons over the life-of-mine.

Meanwhile, a prefeasibility report on the project’s thermal power station component recommends the installation of two 150 MW units.

The report further indicates yearly power generation of between 1 841 GWh and 1 877 GWh, and an additional mineral resource sufficiently large enough to potentially double the current design size to 600 MW or be used in alternate energy-conversion technologies.

Net Present Value/Internal Rate of Return
A financial optimisation study completed on the MCPP in October 2015 revealed that applying an all-in cost margin of between 47.9% and 48.1% could result in the operation’s generating yearly earnings before interest and taxes of between $23.5-million and $23.6-million.

Applying a real discount rate of 5.51%, the best estimated net present value of free cash flow to equity ranges from $214-million to $219-million, with a cash return on capital invested of 726% to 732% and a project payback period of 2.6 years.

The study has further pointed to an equity internal rate of return (IRR) ranging from 131% to 146%, with a project IRR of 54%.

Value
The MCPP technical report estimates a required capital investment of between $46-million and $89-million, and yearly coal sale revenues of between $37-million and $44-million, depending on the selected development option.

The total capital cost of the thermal power plant is estimated at between $640-million and $760-million, depending on the plant configuration.

Duration
Not stated.

Latest Developments
Kibo has completed its definitive power feasibility study (DPFS) on its proposed MCPP.

The company will publish the outcomes of the study following a review process.

Key Contracts and Suppliers
Standard Bank (financial adviser).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Kibo Mining, tel +353 91 865367, fax +353 91 755066 or email info@kibomining.com.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION