France's EDF raises cost estimates for UK's Hinkley Point after review

3rd July 2017

By: Reuters

  

Font size: - +

French state-owned utility EDF flagged a construction cost overrun at its Hinkley Point C nuclear power station in Britain on Monday, in a new blow for a group of EDF projects already facing delays, rising costs and other problems.

After a review, EDF said the cost of completion had increased by 1.5-billion pounds to stand at £19.6-billion ($25.5-billion) – an increase that means its predicted rate of return on investment will fall to 8.5% from 9% previously.

The review, carried out after the final investment decision was made, looked into design and engineering plans, the amount of work that has to be carried out and further discussions with suppliers, EDF said.

EDF also said there was a risk of delayed delivery of the project of 15 months for Unit 1 and nine months for Unit 2, which would add a further £700-million to costs.

The company said it was on track to meet its target of pouring first concrete for the reactor in mid-2019, with unit 1 set to be producing by 2025.

The latest update should have no impact on power supply in Britain, nor should it affect Britain's electricity costs from the first new nuclear plant in decades which is slated to provide 7% of its power needs.

"The UK government negotiated a competitive deal which protects consumers and ensures that all of the cost of construction, including any overruns, sits with the contractor," a spokesperson for the Department for Business, Energy and Industrial Strategy said in an email.

EDF confirmed there would be no impact on that contract.

EDF's announcement follows a report last week in Le Monde newspaper flagging likely cost overruns on Hinkley, although the project received a boost around the same time from news that a prototype being built in Flamanville, France, got the all-clear from safety regulators even though inspectors had found weak spots in its steel reactor cover.

Flamanville itself has faced severe delays, having initially been scheduled for completion by 2012. Another project under construction in Finland using the same so-called European Pressurized Reactor (EPR) technology has also faced delays and cost overruns.

EPR reactors were developed by financially stretched reactor maker Areva, which is in the process of being acquired by EDF following a restructuring of Areva.

Areva and its Finnish customer Teollisuuden Voima (TVO) are locked in a multibillion-dollar legal battle over compensation.

In 2015, Austria launched legal action against the European Commission over the Hinkley Point C project, saying its decision to approve a pricing arrangement that allowed EDF to finance it went against the EU's aim to support renewable energy.

Hinkley Point C was also thrown into doubt in 2016 when newly installed British Prime Minister Theresa May put back a decision to approve it, amid criticism that the guaranteed price negotiated with EDF was too high.

British government approval went ahead in the end, and by March this year, there were 1 600 people working at the site.

EDF is building the plant with China General Nuclear Power Corporation (CGN), which has a 33.5% stake.

Two EPRs are also under construction in Taishan, China. Their bases and covers were manufactured by Creusot Forge in France, the same factory that made the flawed cover for Flamanville.

Edited by Reuters

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION