Eskom welcomes ConCourt judgment around Koeberg tender

21st December 2016

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

  

Font size: - +

Eskom on Wednesday welcomed the decision by the Constitutional Court to dismiss the application by nuclear services provider Westinghouse to review the award of the tender for the replacement of the six steam generators at the Koeberg power station, in Cape Town.

Eskom had, in June 2012, called for expressions of interest for the replacement of the generators for Koeberg and in June 2014 the Eskom board tender committee (BTC) decided to invite Westinghouse Belgium and French energy company Areva, the two bidders for tender negotiations. Eskom awarded the multibillion-rand tender to Areva in August 2014.

Westinghouse Belgium then brought a review application in the High Court to have the tender awarded reviewed and set aside. The High Court dismissed the review application with costs.

The Supreme Court of Appeal turned down Westinghouse Belgium’s plea that the tender be awarded to it and instead remitted it to Eskom for reconsideration.

Areva and Eskom then applied to the Constitutional Court for leave to appeal against the decision of the Supreme Court of Appeal.

Justice Raymond Zondo noted the minority judgment by deputy chief Justice Dikgang Moseneke with acting Justice Ronnie Bosielo, which stated that Eskom was “truly meticulous and proper in its assessment of the bids”.

“The evidence suggests that the BTC process was a hallmark of careful consideration of all relevant factors,” they stated.

Further, the minority judgment stated that: “Westinghouse’s claim that certain vital strategic tender requirements were irregularly considered mid-stream is not supported by a careful evaluation of the tender process. In my respectful view the Supreme Court of Appeal erred by finding that the strategic consideration fell outside the bid evaluation criteria.”

Wednesday’s judgment confirmed that Eskom followed a robust governance process in the awarding of the contracts, the parastatal said.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION