PRASA pushes ahead with fleet refurb plan despite new-train order

8th August 2014

By: Irma Venter

Creamer Media Senior Deputy Editor

  

Font size: - +

The Passenger Rail Agency of South Africa (PRASA) will continue refurbishing its existing Metrorail fleet for another 15 years, despite the R51-billion acquisition of 600 new trains of six cars each signed last year.

Not all the new coaches will come on stream at once, which means the existing fleet has to continue working for quite some time, says Commuter Transport & Locomotives Engineering (CTLE) operations executive Craig Holden.

The 100% black-owned CTLE will refurbish 100 Metrorail coaches for PRASA this financial year at its facility in Nigel as part of the State entity’s general overhaul programme.

CTLE acquired the Union Carriage & Wagon assets from the Murray & Roberts group in 2013.

PRASA is currently refurbishing around 500 coaches a year.

The passenger rail agency has spent R2.1-billion on the refurbishment of 570 coaches since 2010, says PRASA marketing and communications senior manager Nana Zenani.

“The engineering division within PRASA determines which coaches are sent for refur- bishment.”

The CTLE facility has 68 000 m2 under roof and employs 750 people. There is also a welding school on site.

In order to speed up work on the 35-year-old to 50-year-old Metrorail coaches, PRASA has changed its refurbishment methodology.

Repairs used to be done to a general specification on each coach, but this was “too expensive and it took too long”, explains Holden.

Refurbishment is now condition-based, with each coach being individually assessed and repaired.

“This means we can work much faster.”

It takes, on average, 49 days to overhaul a motor coach and 40 days to refurbish a trailer coach.

Local content on the overhaul is around 85%.

The biggest problem in tackling the old coaches is that they have been overhauled three or four times before, says Holden.

To illustrate this, he refers to the action of a screw being inserted into wood three of four times at the same point.

“At some stage, there is nothing left to work with.”

Rewiring is the biggest job when refurbishing the coaches in terms of the work involved, with the most expensive part of the job being the reprofiling of the wheels, refurbishing the bogies and fitting the doors with new controllers, besides others.


CTLE hopes to participate in the R51-billion PRASA recapitalisation programme, says Holden, as there is “enough work for everyone in the industry”.

The company has just completed two locomotive refurbishment contracts for freight hauler Transnet.

CTLE overhauled 110 19Es and 76 15Es for the coal and iron-ore lines.

CTLE is also busy overhauling locomotives for PRASA’s long-distance rail service, and will complete 20 6E units in what is a new contract for the company.

“We hope to produce new bogies soon too,” says Holden. “That will move us up the value chain.”


Around 5 km of rail has been stolen on local council land between the CTLE facility and the larger Gauteng rail network.

This means it is currently impossible to deliver 33 Metrorail coaches, which have already been overhauled, to PRASA. They are left stranded in CTLE’s rail yard.

PRASA can also not deliver new rolling stock in need of refurbishment to CTLE.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION