Creamer Media’s Engineering News Online
Advanced Search
 
 
 
We have detected that the browser you are using is no longer supported. As a result, some content may not display correctly.
We suggest that you upgrade to the latest version of any of the following browsers:
         
close notification
powered by
GOLD 1732.46 $/ozChange: -4.31
PLATINUM 1653.00 $/ozChange: 7.00
R/$ exchange 7.58Change: -0.02
R/€ exchange 10.03Change: -0.12
 
HYDROPOWER
Zambia hydropower upgrade project faces delay
 
1st April 2010
TEXT SIZE
Text Smaller Disabled Text Bigger
 

The commissioning of the upgraded fourth turbine at the Kariba North power station, in Zambia, faces a delay of at least a year, the country’s electricity utility said this week.

Zambia Electricity Supply Corporation (Zesco) power rehabilitation director Musonda Chibulu said that a fire, which broke out in a work area at the hydropower station in September, had damaged some parts of the turbine, which was being reassembled at the time.

Rehabilitation work by contractor Alstom has subsequently been suspended. Some parts had to be replaced and were currently being manufactured in France.

Further, two overhead cranes, which were critical to completing the rehabilitation project, had also been damaged and would likely only be operational again by August this year, said Chibulu.

This meant that the commissioning of the turbine, which had initially been scheduled for March this year, would likely only occur in March 2011, at the earliest.

Despite the delay of the commissioning of the turbine, Zesco’s overall power rehabilitation programme (PRP), which was aimed at replacing and upgrading ageing infrastructure at a number of hydropower stations across Zambia, had led to some improvements in the country’s overall power generation capabilities.

The PRP, which had been funded by Zesco, and through loans from the World Bank, the Development Bank of Southern Africa (DBSA), as well as other international development finance institutions, had been started in the late 1990s to rehabilitate the Kariba North, the Kafue Gorge and the Victoria Falls hydropower stations.

With the work at the Kafue Gorge and the Victoria Falls power stations largely completed, and with the first three turbines at the Kariba North power station running, the PRP had already boosted the country’s overall power output and reduced the need for load shedding in the country.

Once completed, the rehabilitated hydropower stations would add an additional 220 MW to the grid.

Each of the four turbines at Kariba North was being upgraded from 150-MW installed capacity to 180-MW installed capacity.

Further, the PRP had also extended the life of the power plants by 20 years to 30 years, said Chibulu.

In addition, Kariba North power station manager Mwenda Cosmas noted that the PRP had also allowed for the transfer of skills from foreign contractors to local workers, while employment opportunities for locals had been created.

Chibulu added that the transfer of skills would also assist Zesco during the construction and completion of the Kariba North extension project, which involved the adding of a further two 180-MW turbines to the existing station.

He noted that the fire in September had also affected a part of the extension project, but emphasised that there would be no material impact on the completion of the project in 2012.

Chibulu explained that while an investigation into the fire and the area where it occurred was ongoing, the contractor, SinoHydro, continued with other construction areas of the extension project.

With continued economic growth and a “phenomenal” growth in the demand for electricity of about 6% a year on the back of the development of new mines and other industries, the completion of the PRP, as well as new generation projects were needed, said Chibulu.

Further to the $420-million Kariba North extension project, Zesco was also working on implementing the $275-million 120-MW Itezhi Tezhi hydropower station, which was expected to be completed by 2013.

Chibulu noted that the country also had to continue improving its transmission and distribution networks, as well as its demand-side management efforts.

Edited by: Mariaan Webb
FULL Access to Mining Weekly and Engineering News - Subscribe Now!
Subscribe Now Login
 
 
 
 
 
Hide Comments  
 
This article contains no Comments

 
 
All comments must be approved by our editors, click here to read the editorial guidelines for comments. Please allow some time for our editors to approve your comment after posting.
 * Required Fields

image
image
 *
 

 

image
image
 *
 

image
image
 

Verification Image

image
image
 * Please enter the text you see in the above image.
 

 
The Kariba North hydropower station in Zambia
 
The Kariba North hydropower station in Zambia
The Kariba North hydropower station is across from Zimbabwe's Kariba South hydropower station
 
The Kariba North hydropower station is across from Zimbabwe's Kariba South hydropower station
The water inlets for the Kariba North power station
 
The water inlets for the Kariba North power station
The housings for the transformer units of the Kariba North power station
 
The housings for the transformer units of the Kariba North power station
Construction work on the Kariba North Extension project, which would add two additional 180 MW turbines to the existing four at the Kariba North power station.
 
Construction work on the Kariba North Extension project, which would add two additional 180 MW turbines to the existing four at the Kariba North power station.
 
Previous Play Next