Westinghouse Electric Company has filed an application to the High Court of South Africa, charging power utility Eskom with contempt of court, owing to what it said was the utility’s failure to deliver documentation, as ordered by the court, to Westinghouse within five calendar days of September 5. 

The documents related to the R4.3-billion tender for the replacement of steam generators at Eskom’s Koeberg nuclear power station, which the utility had awarded to France’s Areva.

In late October, the utility had issued a statement, insisting that it had “fully complied” with the court order instructing it to hand documentation over to Westinghouse.

However, Westinghouse, on Thursday, said its latest court application had followed several unsuccessful attempts by its legal representatives to obtain “important files relating to the tender selection process”. 

“Westinghouse will continue to exercise all of its legal rights to ensure the actions and decisions of the Eskom management during the tender process are transparent,” it added.

The company believed that, if the timeline for the legal review process, as set down by the court, was adhered to by all parties, there should be no delay with the replacement of the six steam generators at the Koeberg power station in 2018.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Showroom image
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.074 0.128s - 139pq - 4rq
Subscribe Now