First Lesotho Highlands Phase 2 flow expected in 2022
Phase 2 of the Lesotho Highlands Water Pro- ject (LHWP) should supply South Africa with water by 2022, says Lesotho Highlands Devel-opment Authority (LHDA) divisional manager Tente Tente.
A 2009 feasiblity study revealed the water would be available in 2020.
Tente says while the agreement for the second phase was signed in 2011, it was only ratified in 2013, which finally allowed work on the project to kick off.
Tente says, the delivery process for LHWP Phase 2 already has a “cramped, quite hectic” programme, with seven tenders expected in April, seven in May and another seven in June.
The project, estimated to cost R17.5 billion, will include the construction of the Polihale dam, the extension of the Muela hydro- electric complex, the construction of a 38.2 km water transfer tunnel connecting the Polihale reservoir with the hydroelectric complex, access roads to the project sites, camps, power transmission lines and administration centres.
Tente says the LHDA will engage the market through a series of road shows in May, where it will stipulate the “rules of engagement”.
Phase 1 of the LHWP has “not been free of corruption”, he adds, highlighting that there will be strong anticorruption measures in place for the second phase of the scheme.
Tente says the authority learnt many lessons from Phase 1, and refers to a Sotho saying that a new shield is best made tracing the lines of an old one.
“I think this project will be beneficial to the region,” he adds.
The LHWP is a binational interbasin water transfer scheme, which originally aimed for the delivery of 70 m3/s of water to South Africa.
It was envisaged as a four-phase, 30-year scheme, with the treaty for the scheme signed in 1986, following its conception in the 1930s.
It is currently delivering 24 m3/s of water.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation