Tilt-up construction method saves time, money

SUMITOMO PROJECT
Using the tilt-up method on Sumitomo Rubber South Africa’s factory expansion project reduced construction time by about two months

SUMITOMO PROJECT Using the tilt-up method on Sumitomo Rubber South Africa’s factory expansion project reduced construction time by about two months

9th October 2015

By: Donna Slater

Features Deputy Editor and Chief Photographer

  

Font size: - +

Concrete construction company Bedrock Group saved about R5-million on a recent extension of a building at tyre manufacturer Sumitomo’s plant in Ladysmith, KwaZulu-Natal, by implementing the tilt-up construction method, instead of using conventional construction methods.

In November 2013, Sumitomo Rubber South Africa (SRSA) embarked on the project, which expanded its factory space by 2 600 m2. The concrete structure was completed in April.

The SRSA factory uses rubber vulcanising to manufacture tyres and, therefore, any associated buildings require a two-hour fire rating, owing to the high temperatures involved with the manufacture of tyres. Therefore, concrete was chosen for the columns, panels and roof beams of the extension.

Tilting It Up
The tilt-up construction method involves structural elements, such as large columns, being constructed on site and flat on the ground. “The process is quick and simple,” explains Bedrock Group GM David Kitching.

Concrete casting beds are placed horizontally, with the formwork being set on the casting beds, which have been coated with a bond-breaking layer. Following this, rebar is fixed in the formwork and special lifting inserts are attached. The concrete is then poured into moulds, vibrated to eliminate air bubbles and the surface is power-floated to a steel float finish.

Once the concrete is set, the formwork is stripped, revealing an off-shutter finish on the three other sides. In the case of wall panels, the formwork is reset on top of the previous panels. Kitching notes that the process can be repeated up to five times, or more, resulting in stacks of wall panels.

For the SRSA project, the concrete components required a curing period of seven days. However, he says that, in most instances, lifting and tilting of the components can be done within four or five days after the concrete has been poured.

The project required 32 panels measuring 12 m × 6 m and 43 beams measuring
600 mm deep × 450 mm wide × 12 m long, as well as 12 internal columns measuring 800 mm × 600 mm × 12 m.

Kitching adds that using the tilt-up method on SRSA’s expansion reduced construction time by about two months, with all the precast columns erected in a day. The 32 wall panels and 43 beams were erected over five days, with the largest of the panels weighing 38 t.

Once the concrete of the column bases was poured and cured, the panels which had been previously cast and cured were erected and braced in place until the precast beams had been placed and the wall panels secured to the beams using angle cleats and mechanical wedge anchors, thereby stabilising the structure. The braces were then removed. The column bases measured 2 m × 3 m × 600 mm.

Meanwhile, Kitching notes that a major advantage of tilt-up construction is the ease and accuracy at which openings can be made for windows or doors, resulting in easier retrofitting by other contractors and less waste material.

“Bedrock Group actively promotes the use of tilt-up construction to clients, professionals and construction companies,” he says, adding that it is the group’s goal to see all large-envelope buildings, such as warehouses, distribution centres, factories and shopping malls, being built using the technique.

However, Kitching notes that, should uptake in the method increase significantly – which he believes will be the case – it would result in “far more work” than the company could handle. “We are teaching other contractors to do the precast construction, while Bedrock consults on lifting designs, casting bed layouts and crane positions, therefore making tilt-up construction more accessible to contractors,” he says.

Bedrock Group also provides rigging teams to conduct the rigging, lifting and erection aspects that most contractors are wary about, says Kitching.

“It is through this combined approach that tilt-up construction will become the norm,” he concludes.

Edited by Samantha Herbst
Creamer Media Deputy Editor

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.502 0.569s - 152pq - 2rq
Subscribe Now