Solidarity confident of Feb synchronisation of Medupi Unit 6

22nd January 2015

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

Trade union Solidarity on Thursday said there were indications that State-owned power utility Eskom was on track for a mid-February synchronisation of Medupi Unit 6.

Eskom had delayed the synchronisation of the first of the power plant’s power generating units several times; however, Solidarity members and shop stewards have reported to the union that “good progress” was being made after the parastatal missed the December 24 synchronisation deadline.

The embattled Eskom, which has been experiencing major delays and cost overruns at its two coal-fired megaprojects Medupi and Kusile, earlier reported that the synchronisation of Unit 6 was only “weeks away”, with a June 2015 deadline set for bringing the 794 MW unit officially into commercial operation.

Solidarity head of energy Deon Reyneke, who visited the Medupi site on Wednesday, pointed out that the synchronisation would only take place if no unforeseen problems arose.

“We believe and trust that, if all goes well, Eskom will be able to complete the synchronisation of this unit by the middle of February,” he said.

However, Reyneke said Solidarity had launched an investigation into allegations that Eskom was taking “various shortcuts to make up for lost time”.

“If Eskom is disregarding vital measures, the country and its power grid will suffer the consequences for a long time to come,” Reyneke said.

Eskom had not responded to questions posed by Engineering News Online at the time of publication.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.077 0.127s - 139pq - 4rq
Subscribe Now