Long-delayed Lake Kivu methane-gas-to-power project advances
US company Contour Global is finally set to inject 25 MW of electricity into Rwanda’s national grid after years of delay.
Energy Development Corporation Limited (EDCL) MD Agnes Bateta says Contour Global is expected to start generating 25 MW at the Kivuwatt project in September, following completion by Contour Global’s Rwandan subsidiary, Kivuwatt Rwanda, of Phase I of the methane gas electricity generation project on Lake Kivu, in western Rwanda. The company has so far invested $192-million in the project.
“The exploitation of methane gas in Lake Kivu is among the top priority programmes to increase electricity generation,” says Bateta.
The project, which will have a total capacity of 100 MW when completed, is crucial to the East African nation’s energy investment strategy, which seeks to increase the installed capacity from 160 MW at present to 563 MW by 2018.
Studies have shown that Lake Kivu, which covers an area of 2 370 km2, hosts deposits of dissolved methane gas estimated at two-trillion cubic feet and some 10.5-trillion cubic feet of carbon dioxide.
Located on the border between Rwanda and the Democratic Republic of Congo and along the Albertine rift, Lake Kivu is estimated to have the potential to generate 700 MW.
In 2009, the Rwandan government signed a 25-year concession agreement with Contour Global for the exploitation of the resource to generate electricity.
Rwanda has also awarded another US company, Symbion Power, a contract to develop a 50 MW plant on a public–private partnership basis.
Implementation of the Kivuwatt project, however, has been marred by delays related to disputes between Contour Global and its subcontractor, Civicon Kenya.
Completion of the project is critical, as it is part of key generation projects Rwanda is banking on to meet growing electricity demand. Currently, only about 20% of Rwanda’s population have access to electricity.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation